Site 4 = Eastford 66MW
(pre-application completed)

Forth site (Eastford) Owner = Anesco (same as site 2)

(This is basically an extension of site 2 that will use the same track, but is located in the field next door)

Physical Size = ?unknown?

When Planning went in = received 15/10/2024  (published 15/01/25)

Planning Approved = no (Pre application complete)

Whats Next =??

Time line for construction = ??

How long lease period = ??

Power Output = 66MW Capacity 

Energy Consents Unit reference =  ECU00006006 -  Pre Application Complete, decision = Non-EIA  12 Feb 2025

Eastford BESS Map